>>>Installation acceptance of floor wood keel
The wooden keel partition wall is a skeleton made of red and white pine, with gypsum board, wood fiberboard and plywood as the wall of the panel. It has a high processing speed, low labor intensity, light weight, good sound insulation effect and wide application.
1. Construction Procedure for Wood Keel Partition Wall The construction procedure for the wood dragon skeleton is: clear the ground floor → bullet line, find the rules → on the ground with bricks, cement mortar to make the pillow belt (also known as the kick base) → bomb line, back Line to the ceiling and the main structure of the wall → vertical border wall bars → installation along the edge, along the top of the surgery → vertical partition keel → nail horizontal keel → cover panel, set aside socket location and strengthen the pad wood → cover panel processing.
2. Construction specifications for wooden keel partition walls
The wood dragon skeleton should use red, self-sawn pine wood with a size of 40 mm x 70 mm. The spacing of the vertical keel should be taken into consideration in the size of the cover panel, generally between 450 and 600 mm. If there is a doorway, each side should be erected with a Tongtian keel. The horizontal keel should be connected with the vertical keel, and the upper and lower sides of the window and the upper side of the door should be installed with the transverse keel installed along the ground and along the top wooden pole. The two ends of the surgical cylinder should be extended into the brick wall at least l20 mm. To ensure that the partition wall is firmly connected with the original structural wall.
Partition wall panel installation can be performed by referring to the light steel keel cover panel installation method.
3. Acceptance of wooden keel partition walls
The test standards for the wooden keel partition walls are as follows: the partitions are of the correct size and the material specifications are the same; the walls are straight and square, and the corner prescriptions are in close connection with the tight F-edge, along the top wooden beams and the border wall bars, and the keels after the respective transfer should be Firm and straight. Check the partition walls and check with a 2 meter ruler. The surface flatness error is less than 2 mm, the verticality error of the facade is less than 3 mm, and the gap height difference is less than 0.5 mm.
4. Estimated duration of the wooden keel partition wall
The construction of wooden keel partition walls is a construction project with a short construction period. A skilled worker can complete about 7 square meters per day, and installing a partition wall takes about 2 days. The complexity of the wall varies and the duration will vary.
Ceiling-mounted sockets, cement windows, floor tiles, partition doors
Chain Sling Hook,Chain Block Hook,3 Leg Chain Sling,4 Leg Chain
Guangdong Gongyou Lift Slings Machinery CO.,LTD , https://www.workmatehoist.com